Frequently Asked Questions are used to provide additional information and/or statutory guidance not found in State Medicaid Director Letters, State Health Official Letters, or CMCS Informational Bulletins. The different sets of FAQs as originally released can be accessed below.

Showing 21 to 25 of 25 results

We are procuring a COTS solution. This prevents us from providing some of the technical evidence requested in the certification checklists. Will this pose a problem?

CMS encourages the use of COTS solutions where possible, and the milestone review process supports certification of COTS products. The review criteria are intended to be tailorable to support different solutions, including COTS. In this case, the technical criteria in the checklists that do not apply to COTS may be marked ""Not Applicable"" with an explanation as to why they do not apply.

FAQ ID:93986

SHARE URL

How many certification reviews will each state go through with CMS?

It depends. We consider various factors. If a state is developing a complete MMIS solution with one release date, then there will be three reviews: Project Initiation Review, Operational Milestone Review, and MMIS Certification Final Review. If a state has multiple release dates with a modular or agile approach, the state would have one set of three certification reviews with CMS for each module the state would like CMS to certify. Each state will start its certification effort by having an initial consultation with CMS to determine how CMS can schedule milestone reviews that fit with the state's plan.

FAQ ID:94011

SHARE URL

Our state is using an agile approach to develop our MMIS and/or E&E replacement. How will the milestone review milestone review process support this approach?

CMS has developed a milestone review process that is flexible enough to be placed over several development methodologies. CMS wants to ensure that the milestone reviews benefit and do not burden the state. CMS works with each state individually to ensure that the timing of the milestones fit within the state's internal development timeline.

FAQ ID:94001

SHARE URL

When should MMIS and /or E&E milestone reviews be conducted?

Alignment with the state's system development life cycle happens during the Project Initiation phase, specifically during Activity 1: Consult with CMS. The state should incorporate CMS milestone reviews into the state's project schedule. The flexibility is in scheduling, not whether milestone reviews are performed. Decisions made between the state and CMS are documented in the Project Partnership Understanding document and can be updated as needed throughout the life cycle.

FAQ ID:95051

SHARE URL

For E&E and MMIS, how often do the IV&V progress reports have to be submitted to CMS?

At a minimum, quarterly. Depending on the risk of project activity, the state and CMS may agree that more frequent reporting is appropriate. Any frequency greater than quarterly should be captured in the Project Partnership Understanding document.

FAQ ID:95071

SHARE URL