Does the IV&V 18-month compliance period apply to E&E systems?

Yes. The rules pertaining to procuring IV&V contracts (State Medicaid Director Letter 16-010) apply to both E&E and MMIS.

FAQ ID:95061

SHARE URL

Do the documents in the artifacts table need to be created for every module?

In most cases once they are created, the documents will simply be updated to account for the additional modules being planned or developed. A new document is not necessarily created for each module. If a state calls a document by a different name, the state should inform CMS of the name difference.

FAQ ID:95076

SHARE URL

CALT is no longer available. Where should state artifacts and evidence be posted?

Granting CMS direct access to the state's evidence repository is the preferred method for making evidence available to CMS. If that is not possible, the state may make other secure arrangements with CMS, such as using encrypted File Transfer Protocol (FTP). It is critical to follow all Health Insurance Portability and Accountability Act (HIPAA) regulations when submitting evidence that contains personal health information (PHI) and personally identifiable information (PII).

FAQ ID:95081

SHARE URL

Should IV&V progress reports include all the checklist sets every time they submit a progress report?

No. Only the checklists pertaining to the modules undergoing review need to be included, and that only for the report created in preparation for a milestone review. However, the IV&V progress report should include risks and recommendations for the entire project--not just those about to undergo a milestone review.

FAQ ID:95086

SHARE URL

Why are there Standards and Conditions (S&C) and Access and Delivery (A&D) criteria in the Information Architecture checklist?

When streamlining the core checklists (IA, TA and S&C checklists), we found that some criteria fit better in other checklists, so they were moved. To keep traceability simple for the states, we chose to keep the original identifiers for any criteria that were moved. The same holds true for criteria moved to the programmatic tab of the IV&V progress report template.

FAQ ID:95091

SHARE URL

Are Eligibility and Enrollment (E&E) systems now going to be certified the way MMIS systems are certified?

No, E&E systems are not subject to certification. Though the Medicaid Eligibility and Enrollment Toolkit (MEET) was based on the MMIS toolkit, the MEET was created as a way to align how CMS reviews Medicaid enterprise systems and is a means for CMS to provide technical assistance to the states.

FAQ ID:95096

SHARE URL

Based on CMS guidance, states may take up to 18 months to bring an IV&V contractor on board to perform certification tasks or align current IV&V contract to comply with CMS guidance pertaining to scope of services and financial independence. What must the state do if the IV&V contractor's start up is delayed?

IV&V contractor activities must still be performed such as checklist evaluation, artifact review and preparation of IV&V Progress Reports. The state should provide a plan and timeline for how these activities will be supported and performed until the proper IV&V contract can be either procured or aligned with updated CMS guidance on IV&V.

FAQ ID:94866

SHARE URL

What is the applicability of Minimum Acceptable Risk Standards for Exchanges (MARS-E) 2.0 to states' Medicaid Management Information Systems (MMIS)?

MARS-E 2.0 compliance is not required by CMS for states' MMIS, but CMS recommends that states follow applicable national privacy and security standards and practices for their MMIS. MARS-E 2.0 compliance is required for states' Medicaid/CHIP Eligibility and Enrollment (E&E) systems in order to maintain their Authority to Connect with CMS. Link for more information about MARS-E 2.0: https://www.medicaid.gov/federal-policy-guidance/downloads/cib-09-23-2015.pdf (PDF, 105.5 KB).

FAQ ID:94871

SHARE URL

Can state Medicaid agencies access federal financial participation (FFP) to support system changes necessary to meet HIPAA, NIST cybersecurity, or MARS-E 2.0 standards?

For E&E and MMIS, enhanced FFP funding is available at 90 percent via the usual Advanced Planning Document process.

FAQ ID:94876

SHARE URL

Many State demonstrations require that a transition plan to 2014 be submitted by a specified date, in many cases by July 1, 2012. Will CMS provide guidance and technical assistance before then? What specifically is required to be included in the transition plan?

CMS plans to provide technical assistance on transition plans to States through the State Operations and Technical Assistance Team (SOTA) calls and through other calls with the State. We will also be providing additional guidance about the information that should be included in the transition plans. We will consider the transition plans that need to be submitted by the due date as living documents that are open to revision, and will continue to work with States to ensure a seamless transition in 2014 for beneficiaries and States.

Supplemental Links:

 

FAQ ID:93021